|
Lead Time: More
or Less?
by Dave Garwood
Any discussion of lead times almost always reveals these common misconceptions:
If you are not sure if the lead time should be 4 or 6 weeks, what
do you use? The reply is often 8!
If given truth serum, most people feel that if a little lead time
is good, more has to be better!
If delivery of material or product is often late, then increase
the lead time, order sooner and increase the odds material will arrive
on time.
Better to order too early than too late, so err on the high side
when it comes to lead time.
The date material is needed depends on its lead time.
All these traditional views are incorrect and lead to serious supply chain
management problems. The symptoms are excess inventory, excess costs and
missed customer deliveries -- all bad -- and all can be avoided.
Clearing Up the Confusion
Lead times are used up and down the supply chain. For example, every business
has to deal with customer delivery lead times, i.e. how long customers
are willing to wait for a product after ordering it. Customer delivery
lead time has nothing to do with how long it takes to get material and
make the product. Competition determines the accepted delivery lead time.
If your competitor delivers pizza in 30 minutes, you'd better have a very
unique pizza or delivery in 30 minutes. We also have a totally independent
set of lead times to manage the supply side of the supply chain.
Think of the plant floor or supplier as a resource (shown as a funnel
in the graphic below). Work flows into the resource, waits its turn,
gets worked on until complete and flows out. Simple! The resource could
be either people and equipment on the plant floor or a supplier. The lead
time is the sum of three elements: (1) how long it waits (2) how long
it takes to get ready to do the work (set up or changeover time) and (3)
how long it takes to do the work (touch time).

There are several different categories of lead time in every
business. Every business has internal and external lead times. Internal
lead times or manufacturing lead times are for items they make. External
lead times or supplier lead times are for items they buy. There are also
planned and actual lead times for both.
Planned lead time is the elapsed time between ordering material from the
plant or supplier and when you expect to get it. This lead time is primarily
a function of the queue or the time it normally waits to be worked on.
On the plant floor, this is determined by the size of the work-in-process
(WIP). For items coming from suppliers this is a function of their customer
order backlog. In both cases, the wait or queue time is based on an average
Q and it varies. For this reason the term accurate lead time
is an oxymoron.
The actual lead time is how long it actually takes between the time material
is ordered and when it arrives. This also varies each time the item is
made. The actual lead time is a function of the priority of the item ordered.
When the boss says, I want this done today or else," whats
the Q time? Zero! Red tags and Hot Lists can have the same impact. When
a major customer says I need the item today, whats the wait time
or Q in the backlog? Zero! The actual lead time for Hot Jobs
can be compressed to less than the planned lead time. We just cant
compress them all! All other items move back in line and wait longer when
a new order is pushed to the front of the line.
The flip side is also true. When no one seems to be expediting an item,
the actual lead time could stretch into years. Just look at the layers
of dust on some of the items on the plant floor. While the actual lead
time will vary, the average actual lead time should equal the planned
lead time.
Which of the lead time components, wait (Q), set up or run time accounts
for most of the lead time? Of course the answer is Q time. The others
are usually almost insignificant in determining the lead time. The planned
lead time is not precise. A stopwatch is not needed to determine a good
planned lead time. A number that is in the ballpark is all that can be
expected and is needed. Avoid wasting time chasing a precise number.
The actual lead times will be managed by the scheduling system as priorities
are communicated with kanban signals or due dates to determine the relative
priority and thus how long the items wait until its their turn (some
items hit the queue with a sinker on them, usually a red sinker and dont
wait at all). The planned lead times are managed by managing the capacity
of the resource, ie the rate of flow out of the funnel compared to the
rate of flow into the funnel. The average or normal Q is determined by
the difference between the two. See
"Capacity is Infinite" in our article archives. Different
lead times in the business are a function of different parameters.
The Long and the Short of Lead Times
The disadvantage of lead times that are too short are usually readily
understood. Everyone fears being caught short because material was ordered
too late." The natural reaction is to play it safe and order
early, rather than late. This strategy often backfires. Does experience
support the theory that ordering earlier, i.e. increasing the lead time,
increases the odds of on-time delivery? Nope! In fact, experience proves
the opposite. When shipments are late or suppliers are late, it is not
likely that wrong lead times make the top of the Pareto charts of root
causes of late deliveries. Lengthening lead times to solve material shortage
probems usually becomes a liability, not an asset.
The advantages of shorter lead times are often not as obvious, understood
and acknowledged. The lead time determines when material must be received
prior to shipping the product. The longer the lead time, the earlier material
is received and thus the lower the inventory turns. Lead times also determine
when commitments are made to suppliers. Longer lead times mean supplier
commitments are made based on a build schedule that is farther out in
the future and less certain. These commitments can be difficult and costly
to reverse. We can get stuck with the inventory and reduced cash flow.
Shorter lead times also mean we can respond faster to increasing customer
demand.
Assume we are going to be out of stock in 4 weeks on an item. When is
the item needed if the lead time is 2 weeks? When is the item needed if
the lead time is 8 weeks? The answer is the same -- need it in 4 weeks.
We need it when we need it, regardless of the lead time. Lead time just
helps determine when to trigger authorization to the plant floor or supplier
to start producing the item. It also triggers the time when the customer
assumes the financial liability.
All that glitters is not gold. Lead times have a huge impact on the business
and longer lead times are a liability. The focus should be on reducing
planned and actual lead times, not looking for justification for longer
ones.
Lead Time or Cycle Time?
Many JIT, Lean or Flow manufacturing initiatives have been successful
at significantly reducing both planned and actual internal lead times.
The traditional view of arranging the plant floor equipment into functional
departments such as drilling, welding, board subassembly, packaging, etc.,
was replaced by arranging the equipment into work cells or focused factories.
Material flows directly from one step to the next, not stopping. Queue
or wait time is essentially shrunk to zero -- between manufacturing steps.
Cycle time (time to make the product) is reduced. Lead time may not necessarily
be reduced. In some cases, the queue is pushed upstream, i.e. before the
work gets started.Be sure to distinguish between lead time and cycle time
reduction.
Lead times drive inventory investment, flexibility and customer service.
Better planning coupled with a Lean Process will get the desired
result -- shorter lead times.
Lead Time and Flexibility
Flexibility is the ability to change the build or production schedule
up or down, make it happen and incur little or no extra cost or financial
liability. Both the ability to get additional resources resources (capacity)
and material constrain the degree of flexibility. Planned lead time is
a major indicator of the material constraint. The diagram below represents
the items (blue squares) required to build the product. The only difference
in this diagram from company to company is the number of blue squares.

If we determined a planned lead time for each blue square, drew a line
to scale for the length of the lead time and rotated the diagram 90 degrees
counter-clockwise, the result would look like this:

The time fence is the period of time in the future when flexibility starts
to be reduced. In this example, 26 weeks. When the schedule crosses the
fence, we start to "order" items. First B, then F, then D, etc.
If the schedule "jumps" the fence to say week 18, we can't meet
the schedule unless lead time for B and F are compressed. The time fence
cannot be a management mandate or arbitrarily assigned. It is a function
of the cumulative planned lead times. The objective should be to focus
on reducing the lead times as much as possible, which will reduce the
time fence.
Here is an interesting fact: 80% of the time fence is almost always caused
by the supplier lead times. Yet many lean manufacturing initiatives only
focus on reducing internal or plant lead times, not supplier lead times.
There are huge advantages to reducing internal or plant floor lead times.
However, the big flexibility payoff is reducing external or supplier lead
times.
Slashing Lead Times to Increase Profits
Lead time confusion can be a serious disease. Lead times are used in very
business and drive many of the results we see on financial performance
and customer satisfaction reports. Make sure everyone understands the
different types of lead times, what elements need to be carefully managed
and seek continuous improvement to high quality lead times, aka short
ones! It will help lead your business to profitable growth.
|
|